Bridges17FO0005

CLUSTER II-2017: REHABILITATION/MAJOR REPAIR OF EXISTING PERMANENT BRIDGES ALONG MATACON-LIBON-POLANGUI JUNCTION ROAD, & ALBAY WEST COST ROADS

CLUSTER II-2017: REHABILITATION/MAJOR REPAIR OF EXISTING PERMANENT BRIDGES ALONG MATACON-LIBON-POLANGUI JUNCTION ROAD, & ALBAY WEST COST ROADS is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱4,545,941.73. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: WATERTON CONST. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Guinobatan Flood Control, Tandarora Section, Guinobatan, Albay
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0003610

₱956,790.00 · FY2017

Released to San Vicente National High School - Buhi (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,545,941.73

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 16, 2017

Target End

July 14, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.