Buildings and Facilities16FB0146

REHABILITATION/REPAIR/IMPROVEMENT/RESTORATION/UPGRADING OF MANITO RHU 1

REHABILITATION/REPAIR/IMPROVEMENT/RESTORATION/UPGRADING OF MANITO RHU 1 is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱1,625,207.99. Status: Reported complete (DPWH). Contractor on record: NEXT GENERATION CONST AND SUPPLY CORP. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱19,778,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation of Flood Control System along Lava Gully (Left Side) at Mabinit River, Legazpi City, Albay
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0035504

₱259,000.00 · FY2016

Released to J. Marquez National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,625,207.99

Progress

Reported complete (DPWH)

Start Date

January 3, 2018

Target End

March 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.