Construction of Flood Mitigation Structure24ME0005

Construction of Molo Creek Flood Control, Alabel, Sarangani

Construction of Molo Creek Flood Control, Alabel, Sarangani is a DPWH-tracked public work in ALABEL (CAPITAL) (SARANGANI), SARANGANI, Region XII. Reported contract value: ₱48,889,616.12. Status: Reported complete (DPWH). Contractor on record: YURUSA CONST & DEVELOPMENT CORP / EDCL CONST AND SUPPLY. Figures trace to sumbong.

ALABEL (CAPITAL) (SARANGANI), SARANGANI, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Molo Creek Flood Control, Alabel, Sarangani
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0007653

₱1,825,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0007843

₱168,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱48.9M total · 0 flags

4. Implementation

Contract Amount

₱48,889,616.12

Progress

Reported complete (DPWH)

Start Date

February 13, 2024

Target End

September 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.