Roads20FN0069

CONCRETING OF LOCAL ROAD, STA. CRUZ NORTE NIÑO JESUS, IRIGA CITYSTA. 3+600.00 STA. 5+865.00

CONCRETING OF LOCAL ROAD, STA. CRUZ NORTE NIÑO JESUS, IRIGA CITYSTA. 3+600.00 STA. 5+865.00 is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱19,183,933.84. Status: Reported complete (DPWH). Contractor on record: ALRO CONST. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Upstream of Cresini Bridge, San Francisco Section (Sta. 0+358 - Sta. 0+558, right side), Iriga City, Camarines Sur
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Camarines Sur 5th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

91 projects · ₱5.7B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES, BRGY. BUDIAO, DARAGA, ,ALBAY, DARAGA, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱184.5M
Past target date (DPWH On-Going)

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES, UPSTREAM OF CAMALIG BRIDGE, BRGY. 4 (POB)-QUIRANGAY, CAMALIG, ALBAY, CAMALIG, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱164.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO

Region V, Region V

2025₱159.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY BATANG, IROSIN, SORSOGON

Region V, Region V

2024₱158.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG GABAO RIVER, BARANGAY GABAO

Region V, Region V

2024₱158.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO

Region V, Region V

2025₱154.3M
Past target date (DPWH On-Going)
View all 91 projects →

4. Implementation

Contract Amount

₱19,183,933.84

Progress

Reported complete (DPWH)

Start Date

November 24, 2020

Target End

April 26, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.