Water Provision and Storage17OG0079

PACKAGE 1 : A) CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RCWS), JUAN SUMULONG HIGH SCHOOL, BRGY. SAN ROQUE, QC B) CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RCWS) CAMP EMILIO AGUINALDO HIGH SCHOOL, BRGY. BRGY SAN ROQUE, QC C) CONSTRUCTION OF ........

PACKAGE 1 : A) CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RCWS), JUAN SUMULONG HIGH SCHOOL, BRGY. SAN ROQUE, QC B) CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RCWS) CAMP EMILIO AGUINALDO HIGH SCHOOL, BRGY. BRGY SAN ROQUE, QC C) CONSTRUCTION OF ........ is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱3,206,908.66. Status: Reported complete (DPWH). Contractor on record: METRICS CONST. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,206,908.66

Progress

Reported complete (DPWH)

Start Date

October 24, 2017

Target End

January 21, 2018

5. Audit