REPAIR/REHABILITATION/IMPROVEMENT OF BALUCUC-PULILAN ROAD

REPAIR/REHABILITATION/IMPROVEMENT OF BALUCUC-PULILAN ROAD is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱42,816,959.77. Status: Reported complete (DPWH). Contractor on record: MOJAR CONST. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱42,816,959.77

Progress

Reported complete (DPWH)

Start Date

February 28, 2016

Target End

August 15, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.