Flood Control and Drainage18CK0050

REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG RIO CHICO RIVER (TALIMUNDOC-MARIMLA SECTION, RIGHT BANK), DOWNSTREAM OF RIO CHICO BRIDGE), LAPAZ, TARLAC

REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG RIO CHICO RIVER (TALIMUNDOC-MARIMLA SECTION, RIGHT BANK), DOWNSTREAM OF RIO CHICO BRIDGE), LAPAZ, TARLAC is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱39,102,760.43. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱42,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Existing Dike along Rio Chico River (Talimundoc-Marimla Section, Right Bank), Concepcion, Tarlac
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Tarlac 2nd DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

490 projects · ₱18.9B total · 0 flags

Other projects by this contractor

View all 490 projects →

4. Implementation

Contract Amount

₱39,102,760.43

Progress

Reported complete (DPWH)

Start Date

February 15, 2018

Target End

July 11, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.