Buildings and Facilities17HI0044

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT POBLACION, COMPOSTELA, CEBU

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT POBLACION, COMPOSTELA, CEBU is a DPWH-tracked public work in Cebu 5th DEO, Region VII. Reported contract value: ₱1,920,000.00. Status: Reported complete (DPWH). Contractor on record: GEMJOY CONST. Figures trace to dpwh.

Cebu 5th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,920,000.00

Progress

Reported complete (DPWH)

Start Date

December 4, 2017

Target End

March 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.