Buildings and Facilities23FB0002

BIP: CONSTRUCTION OF MULTI-PURPOSE BUILDING PHASE 2, BARANGAY MASAGA, RAPU-RAPU, ALBAY

BIP: CONSTRUCTION OF MULTI-PURPOSE BUILDING PHASE 2, BARANGAY MASAGA, RAPU-RAPU, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱4,800,980.00. Status: Past target date (DPWH On-Going). Contractor on record: 9LEAVES BUILDERS. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at barangay 56 Taysan, Legazpi City, Albay
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Albay 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,800,980.00

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2023

Target End

July 14, 2023

5. Audit