Roads18DQ0093

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - REHABILITATION OF ROAD, BRGY. POBLACION 3, GMA, CAVITE AND CONCRETING OF ROAD, BRGY. MEMIJE TO PULIDO, GMA, CAVITE

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - REHABILITATION OF ROAD, BRGY. POBLACION 3, GMA, CAVITE AND CONCRETING OF ROAD, BRGY. MEMIJE TO PULIDO, GMA, CAVITE is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱14,106,592.44. Status: Reported complete (DPWH). Contractor on record: OMNICON BUILDERS. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱14,106,592.44

Progress

Reported complete (DPWH)

Start Date

July 3, 2018

Target End

October 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.