Roads21HN0095

CONCRETING OF BRGY. GARING FMR (PHASE II), CONSOLACION, CEBU

CONCRETING OF BRGY. GARING FMR (PHASE II), CONSOLACION, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱9,310,000.00. Status: Reported complete (DPWH). Contractor on record: GONZALODO ENT 30681. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 30681

292 projects · ₱8.2B total · 0 flags

4. Implementation

Contract Amount

₱9,310,000.00

Progress

Reported complete (DPWH)

Start Date

May 13, 2021

Target End

December 4, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.