Buildings and Facilities20HH0032

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURE - MULTI PURPOSE / FACILITIES - REHABILITATION OF MULTI - PURPOSE BUILDING, BRGY. PARI-AN, CEBU CITY

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURE - MULTI PURPOSE / FACILITIES - REHABILITATION OF MULTI - PURPOSE BUILDING, BRGY. PARI-AN, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱980,875.56. Status: Reported complete (DPWH). Contractor on record: GOWIL BUILDERS 18733. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 18733

52 projects · ₱637.1M total · 0 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG GUADALUPE RIVER, BAR

Cebu City DEO, Region VII

2024₱49.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITAIONRECONSTRUCTIONUPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PMSHDM-4 OF CONSOLACION -TAYUD - LILOAN ROAD, CHAINAGE 950 - CHAINAGE 2823, CONSOLACION

Cebu 6th DEO, Region VII

2017₱44.9M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROADSYSTEM-ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE - SECONDARY ROADS - 8TH ST. -(S00022CB) CHAINAGE 0 - CHAINAGE 619, (S00384CB) CHAINAGE 0 - CHAINAGE 605, CEBU CITY

Cebu City DEO, Region VII

2022₱44.0M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG GUADALUPE RIVER, PACKAGE 2, BARANGAY SAPANGDAKU,

Cebu City DEO, Region VII

2025₱40.9M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE-TERTIARY ROADS- 5TH ST (S00047CB) CHAINAGE 209-CHAINAGE 424, (S00340CB) CHAINAGE 177-CHAINAGE 302, CEBU CITY

Cebu City DEO, Region VII

2023₱32.2M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM - CONST./UPGRADING/ REHAB. OF DRAINAGE ALONG NAT'L. ROADS - SECONDARY ROADS-CONSOLACION-TAYUD-LILOAN RD -CHAINAGE 90 - CHAINAGE 182, K0014+(-470) -K0014+120, CONSOLACION, CEBU

Cebu 6th DEO, Region VII

2025₱30.2M
Past target date (DPWH On-Going)
View all 52 projects →

4. Implementation

Contract Amount

₱980,875.56

Progress

Reported complete (DPWH)

Start Date

February 3, 2020

Target End

April 17, 2020

5. Audit