Water Provision and Storage25DL0067

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM, WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM, PACKAGE B, BARANGAY SAN ISIDRO, ATIMONAN, QUEZON

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM, WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM, PACKAGE B, BARANGAY SAN ISIDRO, ATIMONAN, QUEZON is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱94,082,071.51. Status: Past target date (DPWH On-Going). Contractor on record: GRAND APEX CONST INC FORMERLY: YUXING CONST INC. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Calauag River, Barangay Villa Aurora, Lopez, Quezon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱94,082,071.51

Progress

Past target date (DPWH On-Going)

Start Date

February 13, 2025

Target End

February 7, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.