Roads21M00020

CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO AMGOO WEAVING CENTER ROAD, TRAPPISTINE MONASTERY AND PARAGLIDING SITE AND VIEW DECK FOR WILD PIG WATCHING AREA, STA. 12+828 - STA. 17+378, BRGY.

CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO AMGOO WEAVING CENTER ROAD, TRAPPISTINE MONASTERY AND PARAGLIDING SITE AND VIEW DECK FOR WILD PIG WATCHING AREA, STA. 12+828 - STA. 17+378, BRGY. is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱89,814,106.47. Status: Reported complete (DPWH). Contractor on record: CHL CONST. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱89,814,106.47

Progress

Reported complete (DPWH)

Start Date

March 25, 2021

Target End

March 24, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.