Buildings and Facilities22BF0063

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING,BARANGAY BACNOR EAST, BURGOS, ISABELA

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING,BARANGAY BACNOR EAST, BURGOS, ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱2,925,448.12. Status: Reported complete (DPWH). Contractor on record: R S K M CONST SERVICES. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱43,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Siffu River Flood Control Structure (Sitio Pakak Section) Brgy. Nuesa, Roxas, Isabela
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Isabela 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,925,448.12

Progress

Reported complete (DPWH)

Start Date

April 4, 2022

Target End

July 2, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.