Buildings and Facilities15JC0113

PROPOSED CONSTRUCTION OF MULTI-PURPOSE BLDG. (COVERED COURT), BARANGAY LINTANGAN, SIBUCO, ZAMBOANGA DEL NORTE 3RD LD.

PROPOSED CONSTRUCTION OF MULTI-PURPOSE BLDG. (COVERED COURT), BARANGAY LINTANGAN, SIBUCO, ZAMBOANGA DEL NORTE 3RD LD. is a DPWH-tracked public work in Zamboanga del Norte 3rd DEO, Region IX. Reported contract value: ₱2,687,878.69. Status: Reported complete (DPWH). Contractor on record: ST JOSEPH CONST AND TRADING. Figures trace to dpwh.

Zamboanga del Norte 3rd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Extension of Flood Control Structure along Dipolog River, Guinles Section (Upstream), Polanco, Zamboanga del Norte
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0030431

₱551,705.00 · FY2016

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱2,687,878.69

Progress

Reported complete (DPWH)

Start Date

February 19, 2016

Target End

July 7, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.