Construction of Flood Mitigation Structure23DD0225

Construction of Revetment along Lawaya River (Balagbag Section), San Juan, Batangas

Construction of Revetment along Lawaya River (Balagbag Section), San Juan, Batangas is a DPWH-tracked public work in SAN JUAN (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱93,605,000.00. Status: Reported complete (DPWH). Contractor on record: 11-16 CONST / HAWK KEY CONST AND GEN MERCHANDISE CORP. Figures trace to sumbong.

SAN JUAN (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures Along San Juan River - Phase 5, Tanauan - Sto. Tomas, Batangas
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 4th District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱93,605,000.00

Progress

Reported complete (DPWH)

Start Date

May 4, 2023

Target End

February 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.