Buildings and Facilities22IA0098

REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING), POBLACION, ALMERIA, BILIRAN (11.620183, 124.378952)

REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING), POBLACION, ALMERIA, BILIRAN (11.620183, 124.378952) is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱14,540,245.94. Status: Reported complete (DPWH). Contractor on record: R K ENGINEERING. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Pulang Bato, Almeria, Biliran
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Biliran DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,540,245.94

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

September 18, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.