Multi Purpose Buildings, School Buildings21FA0035

CLUSTER 17-CONSTRUCTION/REPLACEMENT/REHABILITATION OF COVERED COURT, BARANGAY HALL AND CLASSROOMS IN MALILIPOT, STO. DOMINGO AND BACACAY, ALBAY

CLUSTER 17-CONSTRUCTION/REPLACEMENT/REHABILITATION OF COVERED COURT, BARANGAY HALL AND CLASSROOMS IN MALILIPOT, STO. DOMINGO AND BACACAY, ALBAY is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱24,750,000.00. Status: Reported complete (DPWH). Contractor on record: ROCA BLANCA CONST. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱11,550,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control and Flood Mitigation of the Baclayon River, Brgy. Baclayon, Bacacay, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Albay 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

15 projects · ₱292.8M total · 1 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF DPWH CAMARINES SUR 1ST DEO MOTORPOOL. RAGAY, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2025₱48.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF QAS LABORATORY BUILDING, CAMARINES SUR 1ST DEO, RAGAY, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2025₱48.0M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RIVERBANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG BRGY. ANISLAG -

Albay 2nd DEO, Region V

2024₱47.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

Construction of River Bank Protection Works and Drainage System, Brgy. Imalnod, Legazpi City, Albay

LEGAZPI CITY (CAPITAL) (ALBAY), ALBAY, Region V

2023₱29.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF PINARIC-BAÑADERO ROAD, LE

Region V, Region V

2025₱19.1M
Past target date (DPWH On-Going)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF RIVER BANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG PUROK 5 ILAWOD, CAMALIG,ALBAY

Albay 2nd DEO, Region V

2024₱18.7M
Past target date (DPWH On-Going)
View all 15 projects →

4. Implementation

Contract Amount

₱24,750,000.00

Progress

Reported complete (DPWH)

Start Date

April 15, 2021

Target End

November 10, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.