Construction of Flood Mitigation Structure22II0021

Construction of Flood Control Structure, Phase I, Barangay Bangon, Gamay, Northern Samar

Construction of Flood Control Structure, Phase I, Barangay Bangon, Gamay, Northern Samar is a DPWH-tracked public work in GAMAY (NORTHERN SAMAR), NORTHERN SAMAR, Region VIII. Reported contract value: ₱48,917,835.03. Status: Reported complete (DPWH). Contractor on record: JUPA CONST / JCL CONST AND SUPPLY. Figures trace to sumbong.

GAMAY (NORTHERN SAMAR), NORTHERN SAMAR, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Phase I, Barangay Bangon, Gamay, Northern Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003144

₱399,400,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002817

₱13,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002802

₱5,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱48.9M total · 0 flags

4. Implementation

Contract Amount

₱48,917,835.03

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

November 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.