Buildings and Facilities22PF0152

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT ABATAN, BUGUIAS, BENGUET

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT ABATAN, BUGUIAS, BENGUET is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱29,380,089.51. Status: Reported complete (DPWH). Contractor on record: TADIAN GEN CONST. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Nabalicong, Natubleng, Buguias, Benguet
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Benguet 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

34 projects · ₱308.2M total · 0 flags

Other projects by this contractor

No sat.

CONSTN OF MISSING LINKS/NEW ROADS, SAGADA - BESAO - QUIRINO (VIA LAYLAYA) ROAD, MOUNTAIN PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2020₱47.5M
Reported complete (DPWH)
No sat.

CSSP - TADIAN-SAGADA VIA BESAO ROAD LEADING TO TIRAD PASS VIEW, FIDELISAN FALLS, SUMAGUING CAVE, BALANGAGAN CAVE, AYYUWENG DI LAMBAK ED TADIAN FESTIVAL, KILTEPAN SUNRISE, BESAO SUNSET HANGING COFFINS, ECHO VALLEY, TADIAN, MOUNTAIN PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2020₱28.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, MASLA-DUAGAN ROAD IN SUPPORT OF SUGARCANE, COFFEE, FOOD-PROCESSING AND FURNITURE INDUSTRIES, TADIAN, MOUNTAIN PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2018₱23.5M
Reported complete (DPWH)
No sat.

CSSP-BIP, COMPLETION OF THE OPD COMPLEX AND TERTIARY CLINICAL LABORATORY BUILDING OF BONTOC GENERAL HOSPITAL

Mountain Province 1st DEO, Cordillera Administrative Region

2024₱19.8M
Past target date (DPWH On-Going)
No sat.

BEFF-BATCH 1: CONSTRUCTION OF 2STY4CL, ILANG PRIMARY SCHOOL, TADIAN, MOUNTAIN PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2023₱19.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CSSP-ROLL-IT, ASDAN-KADSO-MASAPA ROAD CONNECTING ASDAN AND KADSO TO THE MT. PROVINCE-ILOCOS SUR NATIONAL ROAD SUPPORTING HEIRLOOM RICE, BANANA CHIPS, COFFEE AND OTHER INDUSTRIES, KAYAN WEST, TADIAN, MOUNTAIN PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2024₱12.3M
Reported complete (DPWH)
View all 34 projects →

4. Implementation

Contract Amount

₱29,380,089.51

Progress

Reported complete (DPWH)

Start Date

October 19, 2022

Target End

December 3, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.