Flood Control and Drainage20CD0005

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER (KING KABAYO SECTION) PHASE IX, SAN MIGUEL, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER (KING KABAYO SECTION) PHASE IX, SAN MIGUEL, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱36,644,392.37. Status: Reported complete (DPWH). Contractor on record: HIGH STRENGTH DEV CORP 31976. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱36,644,392.37

Progress

Reported complete (DPWH)

Start Date

March 3, 2020

Target End

August 19, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.