Flood Control and Drainage20CA0015

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL PROJECTS IN DALAO RIVER, DINALUPIHAN, BATAAN

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL PROJECTS IN DALAO RIVER, DINALUPIHAN, BATAAN is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱43,233,678.29. Status: Reported complete (DPWH). Contractor on record: ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱43,233,678.29

Progress

Reported complete (DPWH)

Start Date

February 18, 2020

Target End

November 8, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.