Roads19HD0107

WIDENING OF ANTONIO Y DE PIO HIGHWAY K0110+446 - K0111+131, TABUELAN, CEBU

WIDENING OF ANTONIO Y DE PIO HIGHWAY K0110+446 - K0111+131, TABUELAN, CEBU is a DPWH-tracked public work in Cebu 4th DEO, Region VII. Reported contract value: ₱19,346,180.00. Status: Reported complete (DPWH). Contractor on record: DUROS DEVELOPMENT CORP. Figures trace to dpwh.

Cebu 4th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROX-19-0007996

₱11,641,000.00 · FY2019

Released to Batangas 4th District Engineering Offi Division of El Salvador City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

260 projects · ₱10.6B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/REPAIR /REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONCRETING/IMPROVEMENT OF BANTAYAN-MADREDIJOS ROAD SECTION STA. 0+000-STA. 13+032

Region VII, Region VII

2016₱238.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTIPURPOSE BUILDING (LILOAN, MUNICIPAL HALL), LILOAN, CEBU

Region VII, Region VII

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), BARANGAY POBL

Region VII, Region VII

2021₱187.2M
Reported complete (DPWH)
No sat.

MFO-1 NATIONAL ROAD NETWORK SERVICES, ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS/SLOPE COLLAPSE, AND LANDSLIDE CEBU-BALAMBAN TRANSCENTRAL HIGHWAY, K0036+790-K0036+880; K0031+910-K0031+985

Region VII, Region VII

2017₱162.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, CEBU NORTH HAGNAYA WHARF RD - K0098 + 829 - K0099 + 889, K0102 + 000 - K0102 + 680, K0105 + 658 - K0105 + 993

Region VII, Region VII

2025₱158.8M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION-PREVENTIVE MAINTENANCE-SECONDARY ROADS - CALUBIAN JCT-SN ISIDRO-TABANGO-VILLABA-PALOMPON RD K1042+285-K1046+979, VILLABA, LEYTE

Leyte 3rd DEO, Region VIII

2025₱142.8M
Reported complete (100% progress, DPWH status On-Going)
View all 260 projects →

4. Implementation

Contract Amount

₱19,346,180.00

Progress

Reported complete (DPWH)

Start Date

July 8, 2019

Target End

December 25, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.