Buildings and Facilities15KG0057

CONSTRUCTION OF MPB AT BARANGAY POBLACION,MATUNGAO,LANAO DEL NORTE

CONSTRUCTION OF MPB AT BARANGAY POBLACION,MATUNGAO,LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱1,899,574.36. Status: Reported complete (DPWH). Contractor on record: LANAO GENESIS CONST SUPPLY. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,899,574.36

Progress

Reported complete (DPWH)

Start Date

January 25, 2016

Target End

April 23, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.