Buildings and Facilities23HB0073

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), CANHAWAY ELEM. SCHOOL, BRGY. CANHAWAY, GUINDULMAN, BOHO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), CANHAWAY ELEM. SCHOOL, BRGY. CANHAWAY, GUINDULMAN, BOHO is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: MUANA CONST AND DEVELOPMENT CORP FORMERLY. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure and Drainage System of Cantomimbo Flood Control, Balilihan, Bohol
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bohol 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

261 projects · ₱5.3B total · 0 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS - CONST. OF FLOOD MITIGATION STRUCTURE ALONG GABAYAN RIVER, CANDIJAY, BOHOL, STA. 0+600.00 - STA. 1+068.00, S

Bohol 3rd DEO, Region VII

2025₱144.7M
Past target date (DPWH On-Going)

Construction of Tumuran - Sarangani River Control, Phase II, Candijay, Bohol

CANDIJAY (BOHOL), BOHOL, Region VII

2024₱144.6M
Reported complete (DPWH)
No sat.

CSSP, CONST./IMPROVEMENT OF VARIOUS INFRA IN SUPPORT OF NATIONAL SECURITY(TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAN AT SEGURIDAD PROGRAM-TIKAS), REHAB. OF 47TH INFANTRY (K) BATTALION HEADQUARTERS-CAMP RAJAH SIKATUNA (PHASE 1),BRGY.KATIPUNAN, CARMEN, BOHOL

Region VII, Region VII

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CSSP, CONST./IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAN AT SEGURIDAD PROGRAM-TIKAS), REHAB. OF 47TH INFANTRY (K) BATTALION HEADQUARTERS-CAMP RAJAH SIKATUNA (PHASE 2), BRGY. KATIPUNAN,

Region VII, Region VII

2025₱141.9M
Past target date (DPWH On-Going)

Construction of Wahig River Control Structure, Pamacsalan Area, Pilar, Bohol

PILAR (BOHOL), BOHOL, Region VII

2024₱130.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING), BRGY. POBLACION, CANDIJAY, BOHOL

Bohol 3rd DEO, Region VII

2023₱99.0M
Reported complete (DPWH)
View all 261 projects →

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

April 11, 2023

Target End

August 13, 2023

5. Audit