Buildings and Facilities18CN0072

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED WALK/PATHWAY, SAN LUIS CENTRAL SCHOOL), BRGY. 1, SAN LUIS, AURORA PROVINCE

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED WALK/PATHWAY, SAN LUIS CENTRAL SCHOOL), BRGY. 1, SAN LUIS, AURORA PROVINCE is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱4,800,610.86. Status: Reported complete (DPWH). Contractor on record: MORNING STEEL CONST. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. Caloocan, Dipaculao, Aurora
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-F-18-0015044

₱1,514,931.00 · FY2018

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱4,800,610.86

Progress

Reported complete (DPWH)

Start Date

July 30, 2018

Target End

November 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.