Buildings and Facilities15BF0135

CONST OF BGRY UEG COMMUNITY CENTER, SAN MARIANO, ISABELA

CONST OF BGRY UEG COMMUNITY CENTER, SAN MARIANO, ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱1,349,798.39. Status: Reported complete (DPWH). Contractor on record: SMT CONST 36331. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,349,798.39

Progress

Reported complete (DPWH)

Start Date

January 24, 2016

Target End

April 2, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.