Construction of Drainage Structure22CN0102

Construction of Drainage Canal (Phase II), Brgy. Quirino, Maria Aurora, Aurora

Construction of Drainage Canal (Phase II), Brgy. Quirino, Maria Aurora, Aurora is a DPWH-tracked public work in MARIA AURORA (AURORA), AURORA, Region III. Reported contract value: ₱39,200,000.00. Status: Reported complete (DPWH). Contractor on record: MORNING STEEL CONST. Figures trace to sumbong.

MARIA AURORA (AURORA), AURORA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Cabituculan East, Maria Aurora, Aurora
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002891

₱787,770,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001729

₱22,200,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001625

₱20,500,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱39,200,000.00

Progress

Reported complete (DPWH)

Start Date

March 1, 2022

Target End

November 16, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.