Flood Control and Drainage24PG0020

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IBULAO RIVER, STA. 342+124 - STA. 342+424, CABA, LAGAWE, IFUGAO

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IBULAO RIVER, STA. 342+124 - STA. 342+424, CABA, LAGAWE, IFUGAO is a DPWH-tracked public work in Ifugao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱19,352,611.35. Status: Past target date (DPWH On-Going). Contractor on record: PAULA MAE BUHONG CONST 26128. Figures trace to dpwh.

Ifugao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Ibulao River, Sta. 342 + 100 - Sta. 342 + 370, Caba, Lagawe, Ifugao
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Ifugao 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 26128

21 projects · ₱479.7M total · 0 flags

Other projects by this contractor

No sat.

RD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL RD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED RD STDS (HDM-4 PROJECT ANALYSIS), KIANGAN-TINOC-BUGUIAS RD, CHAINAGE 43087-CHAINAGE 44907, CHAINAGE 45668 - CHAINAGE 46347, TINOC, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2016₱97.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION / IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURIST DESTINATION - KINAKIN - CAMBULO ROAD LEADING TO KINAKIN & CAMBULO NATIVE VILLAGES RICE TERRACES, BANAO RICE TERRACES

Ifugao 2nd DEO, Cordillera Administrative Region

2017₱60.5M
Past target date (DPWH On-Going)
No sat.

LAGAWE-HINGYON ROAD VIA BURNAY LEADING TO MT. ATUGO AND OTHER TOURISM DESTINATIONS, LAGAWE AND HINGYON, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2023₱49.0M
Reported complete (DPWH)
No sat.

REHABILITATION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG KIANGAN - TINOC - BUGUIAS ROAD, K0354+200 - K0354+500, GUMHANG, TINOC, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2023₱47.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-NUEVA VIZCAYA-IFUGAO-MT. PROVINCE RD. - K0317+667, LAGAWE, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2025₱40.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-NUEVA VIZCAYA-IFUGAO-MT. PROVINCE RD. - K0316+940, K0317+260, K0317+914-K0317+982, LAGAWE, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2025₱33.2M
Past target date (DPWH On-Going)
View all 21 projects →

4. Implementation

Contract Amount

₱19,352,611.35

Progress

Past target date (DPWH On-Going)

Start Date

April 26, 2024

Target End

October 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.