Buildings and Facilities24J00221

CONSTRUCTION OF MULTIPURPOSE HANGAR WITH CONNECTING TAXIWAY, TACTICAL OPERATIONS SQUADRON (TOS), MAPUN, TAWI-TAWI

CONSTRUCTION OF MULTIPURPOSE HANGAR WITH CONNECTING TAXIWAY, TACTICAL OPERATIONS SQUADRON (TOS), MAPUN, TAWI-TAWI is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱33,761,034.78. Status: Past target date (DPWH On-Going). Contractor on record: ATLANTIC ERECTORS INC. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱33,761,034.78

Progress

Past target date (DPWH On-Going)

Start Date

July 10, 2024

Target End

March 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.