Construction of Flood Mitigation Structure24CD0112

Construction of Flood Control Structure along Angat River, Barangay Matictic (Right Side), Norzagaray, Bulacan

Construction of Flood Control Structure along Angat River, Barangay Matictic (Right Side), Norzagaray, Bulacan is a DPWH-tracked public work in NORZAGARAY (BULACAN), BULACAN, Region III. Reported contract value: ₱42,525,092.50. Status: Reported complete (DPWH). Contractor on record: DEVEX INC. Figures trace to sumbong.

NORZAGARAY (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Balagtas River, Barangay San Juan, Purok 4 - Purok 5, Balagtas, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0006660

₱9,979,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007287

₱1,460,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0000163

₱1,078,312.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007288

₱135,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0016339

₱108,080.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱42,525,092.50

Progress

Reported complete (DPWH)

Start Date

March 25, 2024

Target End

October 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.