Flood Control and Drainage18KF0051

CONSTRUCTION/REHABILITATION OF REVETMENT ALONG MANDULOG BRIDGE I (UPSTREAM) INCLUDING ROW, ILIGAN CITY

CONSTRUCTION/REHABILITATION OF REVETMENT ALONG MANDULOG BRIDGE I (UPSTREAM) INCLUDING ROW, ILIGAN CITY is a DPWH-tracked public work in Lanao del Norte 1st DEO, Region X. Reported contract value: ₱35,242,062.71. Status: Reported complete (DPWH). Contractor on record: GRACE CONST CORP. Figures trace to dpwh.

Lanao del Norte 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Consruction/Rehabilitation of Revetment along Mandulog Bridge I (Upstream) including ROW, Iligan City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Lanao del Norte 1st DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱35,242,062.71

Progress

Reported complete (DPWH)

Start Date

February 20, 2018

Target End

November 6, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.