Flood Control and Drainage19IE0040

CONSTRUCTION OF FLOOD CONTROL BARANGAY PADOGACALUBIAN, LEYTE

CONSTRUCTION OF FLOOD CONTROL BARANGAY PADOGACALUBIAN, LEYTE is a DPWH-tracked public work in Leyte 3rd DEO, Region VIII. Reported contract value: ₱1,871,172.96. Status: Reported complete (DPWH). Contractor on record: SILK AND STEEL CONST 25314. Figures trace to dpwh.

Leyte 3rd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,871,172.96

Progress

Reported complete (DPWH)

Start Date

June 5, 2019

Target End

July 2, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.