Roads24PK0075

REPAIR/REHABILITATION OF NATIONAL ROAD ALONG MT. PROVINCE BDRY. - CALANAN - PINUKPUK - ABBUT ROAD, K0454+495 - K0454+557, MABILONG, LUBUAGAN, KALINGA

REPAIR/REHABILITATION OF NATIONAL ROAD ALONG MT. PROVINCE BDRY. - CALANAN - PINUKPUK - ABBUT ROAD, K0454+495 - K0454+557, MABILONG, LUBUAGAN, KALINGA is a DPWH-tracked public work in Upper Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱26,039,281.51. Status: Past target date (DPWH On-Going). Contractor on record: ROCKWELL BUILDERS 46601. Figures trace to dpwh.

Upper Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱6,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sabonac Flood Control along Chico River, Sta. 175 + 270 - Sta. 175 + 350 ( RS. ) , Mabongtot, Lubuagan, Kalinga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Upper Kalinga DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 46601

8 projects · ₱149.1M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE: SECONDARY ROADS - MT PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT RAD - K0450+09

Upper Kalinga DEO, Cordillera Administrative Region

2024₱29.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAINWATER COLLECTOR / WATER SUPPLY SYSTEM - CONSTRUCTION OF LEVEL III WATER SUPPLY PROJECT, LUBUAGAN, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2022₱26.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT: PAVING OF UNPAVED ROADS - TERTIARY ROADS LUBUAGAN - BATONG BUHAY - ABRA BDRY RD K0470 + 050 - K0470 + 573

Upper Kalinga DEO, Cordillera Administrative Region

2021₱20.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: PAVING OF UNPAVED ROADS - TERTIARY ROADS: LUBUAGAN-BATONG BUHAY-ABRA BDRY RD - K0470+573-K0470+953. LUBUAGAN, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2023₱17.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT RD (CAGALU

Lower Kalinga DEO, Cordillera Administrative Region

2023₱15.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONCRETING OF BRGY. MABILONG - BRGY. MABONGTOT FMR, BRGY. MABILONG AND BRGY. MABONGTOT, LUBUAGAN, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2019₱9.8M
Reported complete (DPWH)
View all 8 projects →

4. Implementation

Contract Amount

₱26,039,281.51

Progress

Past target date (DPWH On-Going)

Start Date

August 5, 2024

Target End

June 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.