Roads20JA0004

ROAD WIDENING - ZAMBOANGA CITY-LABUAN-LIMPAPA RD - K1955 + 021 - K1955 + 081 (R/S), K1955 + 205 - K1955 + 216 (L/S), K1957 + 244 -K1957 + 540 (R/S), K1957 + 335 - K1957 + 540 (L/S)

ROAD WIDENING - ZAMBOANGA CITY-LABUAN-LIMPAPA RD - K1955 + 021 - K1955 + 081 (R/S), K1955 + 205 - K1955 + 216 (L/S), K1957 + 244 -K1957 + 540 (R/S), K1957 + 335 - K1957 + 540 (L/S) is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱8,194,522.70. Status: Reported complete (DPWH). Contractor on record: MOTHER'S ROLE CONST 32781. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱8,194,522.70

Progress

Reported complete (DPWH)

Start Date

February 14, 2020

Target End

January 13, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.