Roads20EE0051

CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO SEAWEED PLANTATIONS INBRGY. STA. TERESITADUMARAN, PALAWAN

CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO SEAWEED PLANTATIONS INBRGY. STA. TERESITADUMARAN, PALAWAN is a DPWH-tracked public work in Palawan 1st DEO, Region IV-B. Reported contract value: ₱19,065,244.87. Status: Reported complete (DPWH). Contractor on record: DON VIRGILIO BUILDERS AND SUPPLY. Figures trace to dpwh.

Palawan 1st DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dipuyai Flood Control Project, Palawan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Palawan 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,065,244.87

Progress

Reported complete (DPWH)

Start Date

March 23, 2020

Target End

October 21, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.