Flood Control and Drainage15CH0142

CONSTRUCTION OF LINE CANAL AND CONSTRUCTION OF SLOPE PROTECTION AT BARANGAY PALAT, PORAC, PAMPANGA

CONSTRUCTION OF LINE CANAL AND CONSTRUCTION OF SLOPE PROTECTION AT BARANGAY PALAT, PORAC, PAMPANGA is a DPWH-tracked public work in Pampanga 2nd DEO, Region III. Reported contract value: ₱29,989,206.66. Status: Reported complete (DPWH). Contractor on record: FERDSTAR BUILDERS INC 4965. Figures trace to dpwh.

Pampanga 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 4965

121 projects · ₱7.3B total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS-CONSTRUCTION OF RING DIKE WITH PUMPING STATION (PHASE 2 & 4), MACABEBE-MASANTOL, PROVINCE OF PAMPANGA

Region III, Region III

2024₱354.4M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (STO. TOMAS-MINALIN SECTION), PACKAGE 3, PROVINCE OF PAMPANGA

Region III, Region III

2020₱193.0M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ABACAN RIVER, DIKING AND SLOPE PROTECTION WORKS-PHASE 2, MEXICO, PAMPANGA

Region III, Region III

2025₱170.1M
Past target date (DPWH On-Going)
No sat.

PASIG-MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, CONTRACT PACKAGE NO. 4-B, RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER (UPSTREAM OF MARIKINA BRIDGE) STA. 15+700 TO STA. 15+957 (PHASE 2), RIGHT BANK, MARIKINA CITY

Flood Control Management Cluster, Central Office

2022₱148.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (LUBAO-GUAGUA SECTION), PACKAGE 5, PROVINCE OF PAMPANGA

Region III, Region III

2020₱144.7M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK AT BARANGAY CANDELARIA, MACABEBE, PAMPANGA

Pampanga 1st DEO, Region III

2025₱140.4M
Past target date (DPWH On-Going)
View all 121 projects →

4. Implementation

Contract Amount

₱29,989,206.66

Progress

Reported complete (DPWH)

Start Date

February 29, 2016

Target End

September 25, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.