Flood Control and Drainage18FE0052

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM CONSTRUCTION/REHABILITATION/IMPROVEMENT OCAMPO FLOOD CONTROL(SALVACION CREEK)OCAMPO CAMARINES SUR

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM CONSTRUCTION/REHABILITATION/IMPROVEMENT OCAMPO FLOOD CONTROL(SALVACION CREEK)OCAMPO CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 3rd DEO, Region V. Reported contract value: ₱18,558,638.94. Status: Reported complete (DPWH). Contractor on record: DELPAR CONST. Figures trace to dpwh.

Camarines Sur 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱18,558,638.94

Progress

Reported complete (DPWH)

Start Date

May 27, 2018

Target End

November 14, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.