Buildings and Facilities23HH0085

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM-TIKAS)- CONSTRUCTION OF BARRACKS, ISAFP, CAMP LAPU-LAPU, APAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM-TIKAS)- CONSTRUCTION OF BARRACKS, ISAFP, CAMP LAPU-LAPU, APAS is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱4,882,000.00. Status: Reported complete (DPWH). Contractor on record: VSP STRUCTURE VENTURES CORP FORMERLY: VIRLO CONST 5765. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Guadalupe, Cebu City, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu City DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 5765

129 projects · ₱3.0B total · 0 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER, PHASE 2, LILOAN, CEBU

Region VII, Region VII

2025₱154.3M
Past target date (DPWH On-Going)
No sat.

OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER (DOWNSTREAM), LILOAN, CEBU

Cebu 5th DEO, Region VII

2025₱144.7M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER, COMPOSTELA, CEBU

Cebu 5th DEO, Region VII

2024₱140.2M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONST. OF FLOOD MITIGATION RIVERBANK FACILITIES ALONG CANSAGA RIVER, PACKAGE I, GARING, CONSOLACION, CEBU

Cebu 6th DEO, Region VII

2025₱135.0M
Past target date (DPWH On-Going)
No sat.

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY JUBAY, LILOAN, CEBU

Cebu 5th DEO, Region VII

2025₱99.0M
Past target date (DPWH On-Going)
No sat.

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD WITH DRAINAGE FACILITIES, BRGY UMAPAD, MANDAUE CITY, CEBU

Cebu 6th DEO, Region VII

2023₱98.9M
Reported complete (DPWH)
View all 129 projects →

4. Implementation

Contract Amount

₱4,882,000.00

Progress

Reported complete (DPWH)

Start Date

May 23, 2023

Target End

November 11, 2023

5. Audit