Flood Control and Drainage23AF0206

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN, BRGY. TUDDINGAN, NAGUILIAN, LA UNION

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN, BRGY. TUDDINGAN, NAGUILIAN, LA UNION is a DPWH-tracked public work in La Union 2nd DEO, Region I. Reported contract value: ₱96,488,097.57. Status: Reported complete (DPWH). Contractor on record: ANORE CONST. Figures trace to dpwh.

La Union 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bauang River Basin, Barangays Pudoc to Parian Este, Phase 1, Bauang, La Union
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

La Union 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

120 projects · ₱11.6B total · 12 flags

Other projects by this contractor

No sat.

REHABILITATION OF NORTH NAVOTAS PUMPING STATION AND NAVOTAS NAVIGATION GATE (PHASE 3), NAVOTAS CITY (RE-ADVERTISEMENT)

National Capital Region, National Capital Region

2024₱281.2M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN SECTION (DOWNSTREAM LS), PACKAGE C, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱276.1M
Past target date (DPWH On-Going)
No sat.

COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD, BRGY. SAN ANTONIO SECTION, NAUJAN, ORIENTAL MINDORO

Region IV-B, Region IV-B

2025₱276.1M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN SECTION (LS), PACKAGE B, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱276.0M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF LIGAYA-STA. LUCIA COASTAL ROAD (STA. LUCIA SECTION), SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱247.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ILVITA RIVERBANK PROTECTION WORKS ALONG AMNAY RIVER (DOWNSTREAM), SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱238.3M
Past target date (DPWH On-Going)
View all 120 projects →

4. Implementation

Contract Amount

₱96,488,097.57

Progress

Reported complete (DPWH)

Start Date

March 20, 2024

Target End

December 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.