Roads25JD0031

ROAD WIDENING - PRIMARY ROADS, SINDANGAN-LILOY RD - K1935 + 389 - K1935 + 496, ZAMBOANGA DEL NORTE

ROAD WIDENING - PRIMARY ROADS, SINDANGAN-LILOY RD - K1935 + 389 - K1935 + 496, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 3rd DEO, Region IX. Reported contract value: ₱2,429,931.83. Status: Reported complete (DPWH). Contractor on record: NRMM CONST AND DEV'T CORP 41172. Figures trace to dpwh.

Zamboanga del Norte 3rd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. Dicoyong, Sindangan, Zamboanga del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Zamboanga del Norte 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 41172

204 projects · ₱2.2B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF DPWH ZAMBOANGA DEL SUR 2ND DEO STAFF HOUSE, BARANGAY POBLACION, GUIPOS, ZAMBOANGA DEL SUR

Zamboanga del Sur 2nd DEO, Region IX

2025₱53.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - PRIMARY ROADS - DIPOLOG - SINDANGAN - LILOY ROAD (S01057MN) - K1874+155 - K1874+494

Zamboanga del Norte 2nd DEO, Region IX

2023₱49.0M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PHASE II, BARANGAY BULAWAN, SAN MIGUEL, ZAMBOANGA DEL SUR

Zamboanga del Sur 2nd DEO, Region IX

2025₱49.0M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DUMALIAN RIVER, PHASE II, BARANGAY DUMALIAN, SAN MIGUEL, ZAMBOANGA DEL SUR

Zamboanga del Sur 2nd DEO, Region IX

2025₱49.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG KUMALARANG RIVER LEADING TO SEASHORE, KUMALARANG, ZAMBOANGA DEL SUR

Zamboanga del Sur 2nd DEO, Region IX

2024₱49.0M
Past target date (DPWH On-Going)
No sat.

PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SALUG DIUT RIVER, TUNGAWAN, TAMBULIG, ZAMBOANGA DEL SUR

Zamboanga del Sur 1st DEO, Region IX

2024₱48.9M
Reported complete (DPWH)
View all 204 projects →

4. Implementation

Contract Amount

₱2,429,931.83

Progress

Reported complete (DPWH)

Start Date

February 17, 2025

Target End

March 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.