GAA 2025 SSP25BD0088

BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY LAPI, PEÑABLANCA, CAGAYAN

BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY LAPI, PEÑABLANCA, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱4,899,742.04. Status: Past target date (DPWH On-Going). Contractor on record: PISCES 10 CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Malinta Flood Control Structure along Zinundungan River, Barangay Malinta, Lasam, Cagayan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cagayan 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

7 projects · ₱27.0M total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING, BRGY. GENERAL BALAO, SOLANA, CAGAYAN - PACKAGE 2

Cagayan 3rd DEO, Region II

2024₱4.9M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF PACAC-GRANDE MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), AMULUNG, CAGAYAN

Cagayan 3rd DEO, Region II

2022₱4.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GENERAL BALAO, SOLANA, CAGAYAN

Cagayan 3rd DEO, Region II

2025₱4.8M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY PACAC PIQUEÑO, AMULUNG, CAGAYAN

Cagayan 3rd DEO, Region II

2023₱2.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY LINGU, SOLANA, CAGAYAN

Cagayan 3rd DEO, Region II

2023₱2.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY NANGALISAN, SOLANA, CAGAYAN

Cagayan 3rd DEO, Region II

2023₱2.5M
Reported complete (DPWH)
View all 7 projects →

4. Implementation

Contract Amount

₱4,899,742.04

Progress

Past target date (DPWH On-Going)

Start Date

June 26, 2025

Target End

January 9, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.