Flood Control and Drainage24CL0174

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG OMAYA RIVER, SAN NARCISO, ZAMBALES (PHASE 2)

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG OMAYA RIVER, SAN NARCISO, ZAMBALES (PHASE 2) is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱48,792,154.60. Status: Reported complete (DPWH). Contractor on record: ROAD EDGE TRADING. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Omaya River, San Narciso, Zambales ( Phase 1 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zambales 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

223 projects · ₱12.5B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE, BARANGAY GUINACUTAN, VINZ

Region V, Region V

2025₱144.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE ALONG CULASI, BARANGAY PAM

Region V, Region V

2025₱144.9M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUIBAWA RIVER, BANTACAN, NEW BATAAN, DAVAO DE ORO

Davao de Oro 2nd DEO, Region XI

2024₱144.7M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG PORT BARTON-TDC ROAD SECTION, STA. 017+770-STA. 017+865; STA. 017+914-STA. 017+969; STA. 018+023-STA. 018+244, PALAWAN

Region IV-B, Region IV-B

2022₱144.5M
Reported complete (DPWH)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1398 + 300- K1398 + 600

Misamis Oriental 1st DEO, Region X

2025₱143.3M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF DRAINAGE SYSTEM ALONG DAGUPAN ST., MANILA CITY, PHASE 1

North Manila DEO, National Capital Region

2025₱140.3M
Past target date (DPWH On-Going)
View all 223 projects →

4. Implementation

Contract Amount

₱48,792,154.60

Progress

Reported complete (DPWH)

Start Date

July 2, 2024

Target End

March 28, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.