Roads22IC0056

ASSET PRESERVATION-REHAB./RECONST. OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROADS, BAGAHUPI-BABATNGON-STA. CRUZ-BARUGO-CARIGARA ROAD, K0915+584 - K0915+610, K0918+050 - K0918+650, BABATNGON, LEYTE

ASSET PRESERVATION-REHAB./RECONST. OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROADS, BAGAHUPI-BABATNGON-STA. CRUZ-BARUGO-CARIGARA ROAD, K0915+584 - K0915+610, K0918+050 - K0918+650, BABATNGON, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱67,500,695.18. Status: Reported complete (DPWH). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Tabegui River, Brgy. Villa Magsaysay, Babatngon, Leyte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Leyte 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱67,500,695.18

Progress

Reported complete (DPWH)

Start Date

June 30, 2022

Target End

February 7, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.