Buildings and Facilities20DD0377

CONSTRUCTION OF 4STY20CL, GAUDENCIO B. LONTOK MEMORIAL INTEGRATED SCHOOL, LIPA CITY, BATANGAS

CONSTRUCTION OF 4STY20CL, GAUDENCIO B. LONTOK MEMORIAL INTEGRATED SCHOOL, LIPA CITY, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱71,587,508.02. Status: Reported complete (DPWH). Contractor on record: THREE W BUILDERS INC. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱71,587,508.02

Progress

Reported complete (DPWH)

Start Date

September 4, 2020

Target End

April 16, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.