Flood Control and Drainage21FO0062

REHABILITATION/IMPROVEMENT OF FLOOD MITIGATION STRUCTURE OF CALZADA-BONGORAN, OAS, ALBAY

REHABILITATION/IMPROVEMENT OF FLOOD MITIGATION STRUCTURE OF CALZADA-BONGORAN, OAS, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱29,316,463.94. Status: Reported complete (DPWH). Contractor on record: ELKANKONSTRAK DEVELOPMENT CORP 26220. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱31,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Mitigation Structure of Calzada-Bongoran, Oas, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Albay 3rd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 26220

52 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2024₱141.3M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY 3RD LEGISLATIVE DISTRICT

Region V, Region V

2023₱140.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROAD - SECONDARY ROADS - ALBAY WEST COAST ROAD (MARIGONDON SECTION), KO551 + 680.00 - KO552 + 1

Albay 3rd DEO, Region V

2024₱140.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM-KATUPARAN)-GUINOBATAN-JOVELLAR-DONSOL ROAD LEADING TO PILAR PORT, GUINOBATAN AND JOVELLAR, ALBAY, GU

Region V, Region V

2023₱102.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS-PALANAS-SAN ISIDRO ROAD, JOVELLAR, ALBAY, JOVELLAR, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2025₱93.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - ALBAY WEST COAST RD - K0490 + 700 - K0491 + 140, K0492 + 000 - K049

Albay 3rd DEO, Region V

2025₱82.4M
Past target date (DPWH On-Going)
View all 52 projects →

4. Implementation

Contract Amount

₱29,316,463.94

Progress

Reported complete (DPWH)

Start Date

January 19, 2022

Target End

August 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.