Buildings and Facilities17DK0116

CONSTRUCTION OF TWO(2) UNITS ONE(1) STOREY WORKSHOP BUILDING (REGULAR) @ PAGBILAO GRANDE ISLAND NATIONAL HIGH SCHOOL, PAGBILAO, QUEZON

CONSTRUCTION OF TWO(2) UNITS ONE(1) STOREY WORKSHOP BUILDING (REGULAR) @ PAGBILAO GRANDE ISLAND NATIONAL HIGH SCHOOL, PAGBILAO, QUEZON is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱6,692,370.00. Status: Reported complete (DPWH). Contractor on record: SARCA ESTATE DEVELOPMENT CORP 20520. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱6,692,370.00

Progress

Reported complete (DPWH)

Start Date

November 17, 2017

Target End

April 10, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.