Buildings and Facilities18HK0113

CONSTRUCTION OF TWO (2) STOREY TWO (2) SCIENCE LABORATORY SCHOOL BUILDING AT STA. AGUEDA NATIONAL HIGH SCHOOL, PAMPLONA (9.5MX23.0M)

CONSTRUCTION OF TWO (2) STOREY TWO (2) SCIENCE LABORATORY SCHOOL BUILDING AT STA. AGUEDA NATIONAL HIGH SCHOOL, PAMPLONA (9.5MX23.0M) is a DPWH-tracked public work in Negros Oriental 2nd DEO, Negros Island Region. Reported contract value: ₱8,945,138.43. Status: Reported complete (DPWH). Contractor on record: NEWCON BUILDERS CONST. Figures trace to dpwh.

Negros Oriental 2nd DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱8,945,138.43

Progress

Reported complete (DPWH)

Start Date

July 27, 2018

Target End

February 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.