Buildings and Facilities17LD0006

COMPLETION OF MUNICIPAL GYM, POBLACION, MATANAO, DAVAO DEL SUR

COMPLETION OF MUNICIPAL GYM, POBLACION, MATANAO, DAVAO DEL SUR is a DPWH-tracked public work in Davao del Sur DEO, Region XI. Reported contract value: ₱999,973.20. Status: Reported complete (DPWH). Contractor on record: VERGUZ CONST 26641. Figures trace to dpwh.

Davao del Sur DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱999,973.20

Progress

Reported complete (DPWH)

Start Date

February 28, 2017

Target End

April 13, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.